From where does the Board of Building Code Appeals usually derive its power?

  1. Building code

  2. City or county attorney's office

  3. City Council/county board

  4. Department of building safety

The correct answer is: Building code

The Board of Building Code Appeals typically derives its power from the building code itself. This means that the establishment, authority, and function of the board are outlined within the regulations set forth by the local or state building codes. These codes are designed to ensure that buildings are constructed and maintained safely, which may include provisions for addressing appeals related to building permits, interpretations of the code, or the authority of building officials. When questions or disputes arise regarding code compliance or interpretations, the board provides a mechanism for resolution, reflecting its role as an adjudicating body within the framework of the established building code. While other entities, such as the city or county attorney's office, the city council, or the department of building safety, may influence or interact with the appeals process, the ultimate source of authority for the Board of Building Code Appeals rests within the provisions of the building code itself.