If an application for a permit meets the requirements of an adopted code, what is the typical outcome according to legal guidelines?

  1. A permit shall normally be issued

  2. A permit is usually denied

  3. A request for additional information will be made

  4. The application will be reviewed indefinitely

The correct answer is: A permit shall normally be issued

When an application for a permit fulfills the requirements of an adopted code, the legal guidelines typically dictate that a permit shall normally be issued. This is based on the premise that building codes and regulations are established to ensure safety and compliance; when an application meets these standards, it signifies that the proposed project adheres to the necessary regulations. Issuing a permit under these circumstances reflects the legal intent of the building codes, which is to facilitate construction and development while safeguarding public health and safety. This outcome promotes efficiency in the permitting process, allowing for timely progression of projects that comply with established guidelines. In contrast, options suggesting denial or indefinite review imply a lack of adherence to established legal frameworks or procedural standards. Such scenarios would typically arise only when an application is found lacking in compliance, rather than when it meets the established requirements. Similarly, requesting additional information could be relevant in certain cases but is not the typical outcome when the initial submission aligns with all necessary codes. Hence, the primary expectation in situations where compliance is confirmed is the issuance of a permit.