What is generally not a typical function of the permit technician in processing building permits?

  1. Verifies that submittal documents are complete

  2. Has the applicant sign the application

  3. Distributes issued permits to the tax assessor and other departments

  4. Follows the plan review checklist

The correct answer is: Follows the plan review checklist

The correct answer is that following the plan review checklist is generally not a typical function of the permit technician in processing building permits. The responsibilities of a permit technician focus primarily on managing the permit application process, which includes various administrative tasks. Permit technicians are responsible for tasks such as verifying that the submittal documents are complete. This ensures that the application received meets the required standards before moving forward. Having the applicant sign the application is also a crucial step in formalizing the submission process and ensuring that the applicant is aware of the details of their submissions. Additionally, permit technicians distribute issued permits to different departments, including the tax assessor's office. This helps in proper documentation and ensures that all relevant parties are informed about the issued permits for compliance and tracking purposes. In contrast, following the plan review checklist is typically a task associated with the plan review staff or building officials, who assess the technical aspects of the submitted plans for compliance with building codes and regulations. Therefore, the function of adhering to the plan review checklist does not fall under the typical duties of a permit technician.