Where must the building permit or a copy of it be kept?

  1. In the local municipality office

  2. Posted in the contractor's office

  3. Kept on the site of the work

  4. Sent to the building official

The correct answer is: Kept on the site of the work

The building permit must be kept on the site of the work to ensure that it is readily accessible for inspection by building officials and other authorities. This practice verifies that the work being conducted complies with the approved plans and applicable building codes. By having the permit onsite, it promotes transparency and allows for easier verification that all necessary permits and inspections are in place during the construction process. Keeping the permit on-site is a standard requirement in many jurisdictions because it aids in the regulation of compliance with safety standards and zoning codes. It also provides assurance to inspectors that the project has been authorized and that the contractor is working within the legal framework set by local building codes.