Which of the following is not required to be completed at the time of a framing inspection?

  1. Fire blocking

  2. Roof sheathing

  3. Rough electrical

  4. Insulation

The correct answer is: Insulation

During a framing inspection, the focus is primarily on the structural integrity of the framing elements of the building. This includes checking aspects such as fire blocking, which is critical for preventing the movement of fire and smoke through the structure, as well as roof sheathing, which is important for the overall stability and performance of the roofing system. Rough electrical is also typically included during the framing inspection to ensure that wiring is properly integrated into the framing before covered up by insulation or drywall. Insulation, on the other hand, is not a requirement to be completed at the time of the framing inspection. In fact, insulation is usually installed after the framing and rough mechanical, electrical, and plumbing inspections have been completed. The framing inspection occurs before insulation is installed, as it is essential for the inspector to verify the structural framework without any obstruction. Therefore, insulation completion does not apply to the framing inspection phase.